Splicing Cabinets in Section 3 starting Monday

The terminals are due to arrive today, cabinets are in and installed. We will start splicing on Monday. It is 2 to 3 weeks of splicing then we can start installs in section 3. We will continue to run fiber in Section 4 while the splicing continues, and continue onto section 5. The Aerial crew is hitting their stride and making great progress!

I will post next week on our continued progress.

–Wes